| Case Studies
TRACERCO Diagnostics™ Tower Scan
Tracerco
Asia was invited to apply the TRACERCO Diagnostics™
Tower Scan technique to perform an on-line inspection of
Debutanizer column which was experiencing separation problems.
The objective of the scan was to investigate the cause
of the problem. The column was scanned twice, initially
at 60% capacity and secondly at 100% capacity, after a steam
cleaning process had been carried out to remove suspected
deposit.
The scan lines were specially selected to facilitate the
purpose of the scanning. It was initially planned to carry
out 2 chord scans on the top section of the column, only
1 chord scan could be performed, because of obstructions
(Scan 1). The other chord scan was replaced by a diametric
scan (Scan 2).
For similar reasons:
The initial scans were performed when the column was operating
at 60% capacity. Flooding was expected in view of the high
differential pressure and poor separation.
Scans 1 and 2 through the active tray areas, detected no
vapour above Trays 27 and 28, which indicated flooding.
This condition was further confirmed by Scan 3. This scan
also showed that Trays 29 and 30 were flooded and that the
flooding extended up into the top dome of the column.
The low counts recorded between Tray 27 and the top of
the column indicated that this section of the tower was
full of dense liquid, rather than foam. This type of flooding
is usually associated with a partial blockage that restricts
the down flow of the liquid and causes it to back up in
the column. Such a restriction can be caused by the lay
down of deposits. This then suggested that there was deposition
on Tray 20 and possibly a partial plugging of the Tray 28
downcomer.
Tray 26 appeared to be in good condition and was carrying
between 50-100mm liquid.
However, all of the trays from Tray 25 down to Tray 11 were
holding significantly less liquid and appear to be more
or less “dry”. The worst in this respect was
Tray 18.
Though a very low liquid level is often indicative of
partial damage or damage to the tray there was insufficient
evidence from these scans to confirm this view. It seemed
equally likely that the low liquid levels were caused by
the much-reduced down flow of liquid, caused by the flow
restrictions observed further up the tower.
Scans 1 and 2 from Tray 16 down to Tray 11 showed that
that these trays were also holding very little liquid. Again,
this may be due to partial damage or maybe caused by the
restricted liquid down flow.
Beneath the cone, Scans 4 and 5 covered the region between
Tray 10 and Tray 1. The profiles for Trays 10-1 indicated
that the trays were in good condition and were carrying
reasonable depths of liquid of around
100–150 mm.
The second scan was performed when the column was operating
at 100% capacity. Tracerco was informed that a “steaming”
process had been carried out to remove any deposit that
might have caused restriction to the liquid flow that had
been observed at Tray 27 in the previous scan. It should
be noted that the temperature at Tray 23 was approximately
40oC lower than for the scans carried out the previous week.
This suggested that the top section of the column was the
likely problem area.
Scan 1A, 2A and 3A showed that the column was flooded from
the top tangent down to tray 22. The density of the liquid
in the flooded region was less than that observed in the
scans of 15-16 July, which suggested that there was vapour
passing through the liquid, indicating that there had been
some reduction in the deposits restricting the flow.
Below Tray 22, there was no sign of flooding. Rather, the
observed counts in the vapour spaces above the trays coincided
with the Free Vapour Count, indicating complete disengagement
of the liquid and vapour. However Trays 21-17 were still
carrying very little liquid.
The initial scans revealed that the top section of the
column, between the tangent line and Tray 27, was flooded.
It is believed that this was caused by deposits restricting
the flow of liquid down the tower and implies partial plugging
of the Tray 28 downcomer.
Beneath Tray 27 there was excellent disengagement of the
liquid and vapour above all the trays.
Trays 25 to 11 were carrying very little liquid and Trays
18 and 14 appeared to be “dry”. Though the possibility
of partial tray damage cannot be ruled out, it seemed more
likely, in view of the flow restriction observed further
up the tower, that the low levels of liquid on the trays
reflected the greatly reduced flow of liquid down the column.
All of the other trays, from Tray 10 down to Tray 1 appeared
to be operating satisfactorily.
The second scans showed that flooding was again observed
in the top section of the column but the flood now extended
from the top tangent line down to Tray 22. It seems likely
that the column cleaning operation had flushed the deposits
that were originally causing the restriction at Tray 27
down to Tray 22.
After the Refiner had cleared the flow restriction, either
by steam cleaning or by physical removal at shutdown Tracerco
Asia’s techniques were able to pinpoint the cause
of the column’s separation problems and help the plant
to effect speedy repairs and a rapid return to full production
of high quality product.
<< back
|