| Case Studies
TRACERCO Diagnostics™ Tower Scan
Diagnosing the cause of poor tower performance
Tracerco helped to diagnose the cause of poor tower performance
which resulted in a shorter than expected shutdown and eliminated
the need to order costly trays. Following a unit power failure,
the column was not able to make even marginal specification
product at the desired rates. It was thought that the sudden
shutdown had damaged the trays in the column. A computer
simulation model of the column indicated that, at the prevailing
operating conditions, 30% of the trays would have been malfunctioning
for this to occur. Since the product was in demand, a shutdown
to replace the trays suspected of being damaged was scheduled
for 3 weeks after the incident. Ordering the replacement
trays on such short notice would demand a premium price
from the manufacturer and extra trays would have to be ordered
to have on hand as spares, since the true extent of the
damage was unknown. A maintenance engineer recommended using
the TRACERCO Diagnostics™ Tower Scan to identify
the extent of the damage.

The 100ft. scan was completed in approximately 5 hours
and a preliminary interpretation was available 30 minutes
later. The scan results indicated that no major tray damage
had occurred in the column. The separation problem appeared
to be caused by a severe vapour related flood condition
occurring above the feed tray. A possible cause was plugged
trays, since the column handled material that could cause
fouling. The decision was made to inspect the column during
the shutdown, but not to order any trays. The inspection
revealed pluggage on the trays above the feed point. This
was probably caused by material solidifying on the trays
after the abrupt shutdown. A substantial cost saving was
realised by the shortened shutdown and by not ordering replacement
trays.
<< back
|